1 | Projects.LocationTable | (Baltim Concession), close to the Mediterranean Sea coast | |||||||||||||||||||||||||||
2 | Projects.Client | PETROBEL / ENI | |||||||||||||||||||||||||||
3 | Projects.Owner | PETROBEL / ENI ![]() | |||||||||||||||||||||||||||
4 | Projects.TypeOfParticipation | Construction Contractor | |||||||||||||||||||||||||||
5 | Projects.ContractValue | 28,453,395 US$ | |||||||||||||||||||||||||||
6 | Projects.Duration | 12 Months | |||||||||||||||||||||||||||
7 | Projects.StartDate - Projects.EndDate | 2018-07-01 Projects.To 2019-06-01 | |||||||||||||||||||||||||||
8 | Projects.ProjectDescription | - The project is to transport the gas production of the new platform BSW to the shoreline at Petrobel NIDOCO -11 Area & eventually to ABU Madi plant (via on onshore pipeline. -The installation of a new conductor Platform (BSW& Umbilical Installation. - (multiphase) subsea pipeline Installation | |||||||||||||||||||||||||||
9 | Projects.ScopeOfWork | 1-Site Preparation for 26” Pipeline shore Pulling Pre-Lay survey and anchor clearance. On-Shore Site preparation for the Sea line Approach. Construction of Causeway (Length 287 m). Driving of Sheet Piles (928 Sheet piles). Cofferdam Excavation & Backfilling (5740m3). Site Reinstatement. 2-26” Offshore PipelineTransportation and Installation Transition Activities. Onshore & Offshore line Pipes Transportation. Beach pull Activities (81 joints and Length 0.967 km). Normal Laying of 26” Pipeline (1405 joints and length 17.168 km). Pre-commissioning and Stabilization Activities. Post Trenching Activities 3-BSW Platform Transportation & Installation Activities : SSIV (Subsea Safety Isolation Valve). Subsea Template (93.6 Ton) and 4 pin Piles. BSW Jacket (710 Ton) with 4 Foundation Piles. BSW Deck (1690 Ton). 8 non-Metrology Spools & 2 Metrology Spools. Umbilical Installation. Hook Up Activities on BSW Platform | |||||||||||||||||||||||||||
10 | Projects.MarineVesselsUsedInTheProject | 1- PMS-12 - 600 Tons Derrick Pipe Laying Barge 2- PMS-MAYO DPII DSV Sat Diving 3- PMS-32 AHTS 4- PMS-4 Tug Boat 5- PMS-5 Tug Boat | |||||||||||||||||||||||||||
11 | Projects.WorkVolume |
|