







1 | Location | Mediterranean Sea | |||||||||||||||
2 | Client | Petrobel | |||||||||||||||
3 | Owner | Petrobel / Eni ![]() | |||||||||||||||
4 | Type of participation | Main Contractor | |||||||||||||||
5 | Contract value | 27,000,000 US$ | |||||||||||||||
6 | Duration | 8 months | |||||||||||||||
7 | Start Date - End Date | 2022-04-10 to 2023-11-06 | |||||||||||||||
8 | Project description | 1- Trenching & Beach Pull activities 2- Laying Internal Cladding 14” Pipe Line from PP-2 to Petreco onshore to maximize crude oil production in the Belayim fields in the Patreco area. | |||||||||||||||
9 | Scope Of Work | Trenching activities Trenching activities & causeway construction + Access road + construction of pulling winch base, Excavation ,beach pulling operation, backfilling activities cause way removal and site reinstatement Internal Cladding Pipe Line Laying Activities Receiving line pipes @ Ain Sokhna Offshore transportation of line pipes from Ain Sokhna port to PMS-12 at Belayim Field Survey for Barge anchors positions before deployment Pre-crossing installation Shore pull and normal Laying for 14” P/L from Petrico shore area to PP-2 P/F with total length 10.7 Km. Diving Activities Supporting Pipe Line Laying Monitoring for touch down point during laying Free span rectification Stabilization Mattresses installation Pipe Line Tie in: 14” Riser installation at PP-2 P/F Install 14” spools (4 Non Metrology+1 Metrology spools) Pipe Line Tie in : Pigging , Leak test & hydro-test | |||||||||||||||
10 | Marine vessels used in the project | 1- PMS-12 Derrick Pipe Laying Barge utilized in the project for Automatic Pipe line laying 2- PMS-17 DPII Derrick Barge utilized in the project for Pigging & Tie in Activities 3- PMS-11 Derrick Pipe Laying Barge utilized in the project for Free Span Activities 4- PMS-31 AHTS 5-5 Rented Supply Vessel / AHTS | |||||||||||||||
11 | Work volume |
|